Courtyard by Marriott Portfolio | Exterior Re-Imaging

Scope: Exterior re-imaging program for a total of six hotels 

Individual Project Construction Budget: $886,000

Our Role: Full-service project management to include brand approvals, budget, schedule, design and planning, construction and project management, and accounting

Schedule: 12-week construction schedule for each project

HVMG savings from Marriott’s provided budget analysis:

  • Feature Frame Structure – Constructed of wood in lieu of steel (existing structure is wood)
  • Multiple renovations with simultaneous schedule
  • Nichiha Installation- Existing structure is CMU, not EIFS, which allowed Nichiha framing to be directly applied to CMU in lieu of substrate
  • Sourced local, exterior specialty General Contractor, in lieu of full scope General Contractor

Before

After

Read Other Case Studies

Elevate Logo
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.